Enerjisa Power Generation, an endeavor of Sabanci Holding and E.ON, is building up the Bandirma II regular gas-let go consolidated cycle station inside of the Balikesir region of Turkey. 
The station is being raised on board the predominant 930MW Bandirma power plant, the biggest fossil fuel station in Turkey. The 600MW force venture is being built with Associate in Nursing measurable speculation of $900m and is customary for commission in 2016. it's relied upon to control at Associate in Nursing strength rate of over hr. 

The undertaking is expected to make more than one,000 development occupations and an additional forty employments once operational. 

Bandirma-I CCPP points of interest 


Enerjisa started industrial operations at its Bandirma-I consolidated cycle station (CCPP) in 2010. With a web strength of more than fifty nine, it's Turkey's best service station Associate in Nursingd brags a yearly power era capacity of more than seven,000 gigawatt hours (GWh). 

The €550m ($699m) Bandirma-I CCPP took twenty six months to finish. 

Bandirma II joined cycle station make-up 

The Bandirma II CCPP is being produced on the southern bank of the sea of Marmara near the Bandirma town in Balikesir territory, and spreads a complete space of more than eighty five,000m2. 

Bandirma II are one shaft style joined cycle station containing a SGT5-8000H turbine, a SST5-5000 turbine and a SGen5-3000W water cooled generator from Siemens. The plant will increment to full power era in just half-hour. 

The Siemens SGT5-8000H turbine, with gross force yield of 400MW, produces more than 570MW in consolidated cycle operations. The predominant four stage turbine is furnished with speedy acting variable aide vanes to accomplish speedier games ability. It utilizes Siemens water powered leeway advancement (HCO) dynamic turning motor freedom framework to balance motor execution misfortunes. 

The SST5-5000 turbine, that incorporates a joined high-weight/halfway weight reverse stream barrel and a twofold stream nonaggressive chamber, is intended to control at a steam weight of up to 190bar and steam temperature of up to 600°C. The rotational motor offers an impact yield go between 120MW to 500MW in consolidated cycle application. 

The Bandirma II plant can utilize a dry sort cooling framework with a 135m high cooling framework. 

Era and transmission of force from Bandirma II station 

The following hot gasses from the burning technique are sent to the waste warmth evaporator wherever steam are created. the new and forceful steam can then be sent to demonstrate the turbine, for second level power era at the plant.Natural gas blended with over controlled gas are blazed inside of the ignition chamber before going through the turbine for beginning level power era. 

Steam released from the turning motor are consolidated into water in an exceptionally condenser exploitation cooling water from the tower. Water gathered at untouched low of the condenser are sent back to the boilers for extra warming. 

The power created by the venture is wanted to be transmitted either to the Balikesir common electrical gadget station by means of Associate in Nursing 85km long link, or to Karabiga station through a 70km long link. 

Common gas give 

Common gas for the Bandirma II station are prepared from the Turkey/Greece fossil fuel pipeline settled near the venture site. 

Contractual workers connected the Bandirma II power venture improvement 


Siemens was granted the corrections officer development contract for the Bandirma II station in Gregorian logbook month 2013. The composed understanding degree incorporates the accessibility of turbines and generators. It furthermore incorporates the entire electrical framework, including a 400kV high-voltage switchgear establishment, furthermore the SPPA-T3000 instrumentation and framework. The Benson-sort heat recuperation steam generator (HRSG) to be utilized at the office plant are manufacturing plant made by NEM. 

Kalemci Yapi was subcontracted by Siemens to direct polite works, though Koza Insaat was locked in to perform earth works. DOKAY-EIA Environmental Engineering was locked in to compose the natural effect appraisal (EIA) application for the undertaking.